[G.R.
No. 139512. January 23, 2002]
SOLID
HOMES, INC., etc. vs. MANUEL SANCHEZ, et al.
FIRST DIVISION
Gentlemen:
Quoted hereunder, for your information, is a
resolution of this Court dated 23 JAN
2002.
G.R. No. 139512 (Solid Homes,
Inc., etc. vs. Manuel Sanchez, et al.)
Petitioner assails the decision of the Court of Appeals in CA-G.R. SP
No. 47907 affirming the decision of the Office of the President. The procedural
antecedents are undisputed. As found by the Court of Appeals:
Medina
Foods, Industries, Inc. entered into several contracts to sell parcels of land
to Manuel Sanchez. The following are the terms and considerations in the
transactions, to wit:
“1. Contract to sell dated March
19, 1991 for Lot Nos. 8-A, 8-B, 8-D, 8-E, 8-F, 8-G, 7-A, 7-B and Lot 7-G all
located at Loyola Grand Villas, Quezon City.
Contract
Price : P36,308,572.50
Down
Payment : 5,000,000.00
Balance : 31,308,572.50
Terms : P 2,850.00/sq.m. for all the above lots except for Lot No. 7-B which has a Contract Price of P4,773,322.50 at P1.5 M/month for 15 months and p8,808,572.50 on or before 16th month.
2. Contract to Sell dated July 3, 1990 for Lot No. 7-F.
Contract
Price : P2,707,500.00
Down
Payment : 1,000,000.00
Balance : 1,707,500.00
Terms :
P 2,707.50/sq.m.
P 106,718.75/month
for 16 months
3. Contract to Sell dated July 14, 1990 for Lot No. 7-E.
Contract
Price : P2,780,602.50
Down
Payment : 1,500,000.00
Balance : 2,707.50/sq.m.
P
28,060.25/month
for 10 months”
To insure
compliance with their respective obligations under the said contracts, the
parties entered into an Escrow Agreement with Far East Bank and Trust Company
(FEBTC). Pursuant to the Escrow Agreement, Medina Foods Industries, Inc.,
through its attorney-in-fact Solid homes, Inc., surrendered and delivered to
FEBTC the owner’s duplicate copies of Transfer Certificates of Titles for the
following lots: 7-A, 7-B, 7-E, 7-F, 7-G, 8-A to 8-G.
Manuel
Sanchez thereafter commenced to pay his obligation, which was, however,
suspended in October 1990. On account of said suspension, Solid Homes on August
13, 1991 made a demand on Sanchez to pay his obligations. Sanchez replied
asserting that under their contract, he is justified to suspend payment of his
obligation since Solid Homes had failed to develop the projects within six (6)
months from the execution of the contracts. Repeated demands were made on
Sanchez but the latter merely reiterated his position that there was
non-development of the project.
When
Sanchez failed to comply with his obligation, Solid Homes wrote to Sanchez on
March 18, 1992 informing him of its desire to rescind and cancel the contracts
to sell and apply and credit whatever payments made to an equivalent area based
on P2,850.00 per square meter, in accordance with paragraph 7 of the Contracts
to Sell. On April 1, 1993, Solid Homes sent Sanchez a Notice of Formal Notarial
Rescission with Affidavit of Formal Notarial Rescission.
On July 3,
1993, Solid Homes, Inc. filed a petition for Confirmation of Rescission,
Delivery of Title and Damages against Manuel Sanchez and FEBTC before the
Housing and Land Use Regulatory Board (HLURB). The petition was docketed as
HLRB Case No. REM-070293-5483.
x x x
On April
27, 1994, the Arbiter issued a decision in favor of the complainant, the
dispositive portion of which reads:
“WHEREFORE,
judgment is hereby rendered as follows:
1. Confirming the rescission and cancellation of
the Contract to Sell respectively dated March 19, 1991, July 3, 1990 and June
14, 1990 and the crediting of whatever payments made by Manuel Sanchez to an
equivalent area based on P2,850.00 per square meter;
2. Requiring Far East Bank and Trust Company
within 30 days from finality hereof to return to the Complainant the following
Transfer Certificate of Title Nos. 22457, 22456, 22458, 22455, 22459, 22460,
22422, 22438, 22443, 22439 and 22442 and all titles delivered into it because
of escrow agreement;
3. Adjudging Sanchez and FEB to pay jointly and
solidarily the Complainant the amount of P20,000.00 as damages and P20,000.00
as attorney’s fees. No pronouncement as to cost of suit.”
Sanchez
filed a petition for review of the said decision with the HLURB Commissioners.
On October 11, 1995, Sanchez filed a
motion for ocular inspection contending that the primary issue in the case,
which is whether or not there is full development of the subject properties,
can best be settled by an ocular inspection of the said properties. This motion
was granted by the HLURB in an Order dated December 1, 1995. The HLURB then
ordered the creation of an inspection team to perform an ocular inspection “to
finally assess and evaluate the situation in the subdivision site.”
On
February 26, 1996, the Inspection Team submitted its report in compliance with
the December 1, 1995 Order of the HLTJRB. The Board then rendered its Decision
on May 21, 1996, reversing the findings of the Arbiter. It held that according
to the evidence, the project has not been completed and therefore, Sanchez “was
well within his right in suspending payments of amortization to complainants
and hence, the rescission of the contract is not valid as Section 23 of P.D.
No. 957.” The dispositive portion of said decision states:
“WHEREFORE,
premises considered, the decision of the Office a quo is hereby SET ASIDE and a
new judgment is hereby entered as follows:
1. Declaring the cancellation of the contract as
null and void.
2. Ordering respondent to continue to pay the
amortization to complainant upon complete development of the project in
accordance with the original terms of the contracts.
3. Ordering FEBTC to continue to hold the titles
of the lots in Escrow until after the parties have fully complied their
obligation thereto.
4. Ordering complainant to pay respondent nominal
damages in the amount of P100,000.00 within 15 days from finality hereof.
5. Ordering complainant to pay this Board the
amount of P10,000.00 as and by way of administrative fine.
SO
ORDERED.”
Solid
Homes, Inc. moved to reconsider the above-mentioned decision. On February 6,
1997, the Board reconsidered its earlier decision.
As shown
in the aforementioned inspection reports, the only significant uncompleted item
is the electrical installations. For this purpose, we take judicial notice of
the fact that this facility is not put into place until after the houses in the
subdivision are constructed. In fact in this project, those lots where houses
have been erected have already been provided with electricity. Since what were
sold were only parcels of lots, installation of MERALCO electrical lines will
necessarily have to be deferred pending construction of houses to be serviced.
While we
find evidence pointing to the problem of non-maintenance, the same is brought
about by the ordinary wear and tear to which the subject property is exposed
and for which we cannot fault the complainant for non-development, for indeed
there was development. Non-maintenance of the facilities in the subdivision is
not the ground referred to under Section 23 of PD 957, which would justify the
buyer in suspending his monthly amortizations, but non-development.
The Board
thus reinstated the Arbiter’s Decision with some modifications, to wit:
“1. The amount of P16,820,156.20 paid by respondent
Sanchez to complainant be credited to an equivalent area based on the rate
agreed upon in the contracts to sell;
2. Complainant to execute the Deed of Sale in
favor of respondent Sanchez covering so much area of the lots that the amount
of P16,820,156.20 shall fully pay;
3. Ordering complainant to maintain the project in
accordance with the approved plan until the same is transferred to the
Homeowner’s Association or the Local Government concerned as the case may be;
and
4. Ordering FEBTC to continue to hold in escrow
the titles equivalent to the aforestated amount and shall deliver the same to
respondent Sanchez and release the rest of the titles covered by the Escrow
Agreement to the complainant within 30 days from finality of this decision.
SO
ORDERED.”
Sanchez
then filed an appeal before the Office of the President. On April 16, 1998, the
Office of the President rendered a decision reversing the appealed decision and
reinstating the May 21, 1996 Decision of the HLURB with some modifications with
respect to the amount of P16,820,156.20 which had been paid by Sanchez which is
to be credited in payment of an equivalent area to be chosen by Sanchez and the
execution of the appropriate deed of sale as well as the holding of the
remaining titles by FEBTC under the escrow agreement until after the parties
shall have fully complied with their respective obligations.
x x x
It appears
from the records that from the time the petitioner made demands on Sanchez to
pay his obligations, the latter had consistently claimed that the subdivision has
not been developed, thus justifying his non-payment of the lots therein.
It was
shown, however, that throughout the pendency of the case, the HLURB or its
authorized office had issued three (3) ocular inspection reports on the
percentage of developments on the specific properties subject of the sale which
were conducted on three (3) separate occasions (June 11, 1993, September 11,
1995 and February 28, 1996). The following reports show the progress of the
developments:
6.11.93 9.11.95 2.28.96
1. Road 90% 100%
2. Sidewalk 100% 100% 100%
3. Curbs/Gutter 100% 100%
4. Drainage System 100% 100% 100%
5. Water
System 80% 100%
6. Electrical
Distribution
System 100% 20% 50%
7. Pavement 100%
The
results of all these inspections show substantial compliance on the part of
complainant. It appears, however, that while on appeal before the Office of the
President, said office required the HLURB to comment on the said appeal. On the
basis of the report of the HLURB, the Office of the President reversed the
earlier findings of the HLURB. (Rollo, pp.
238-244.)
Aggrieved, petitioner sought relief before the Court of Appeals, which
affirmed the decision of the Office of the President.
Petitioner contends that the order of the Office of the President
directing the HLURB to file a comment on the appeal on its own decision was
“unprocedural.” The filing of such comment, according to petitioner, is not
sanctioned by Administrative Order No. 18, the rules governing appeals to the
Office of the President. In this regard, the Court of Appeals held, and this
Court agrees, that:
This
contention is without merit. In administrative cases, the rules of procedure
are not applied in a very rigid, technical sense. Rules of procedure are used
only to help secure substantial justice. (City of Cebu vs. Court of Appeals,
258 SCRA 175). (Rollo, p. 244.)
Notably, Administrative Order No. 18 does not prohibit the Office of the
President from requiring such comment. In any case, there is no showing that
petitioner objected to said order. It is therefore estopped from raising that
alleged defect on appeal.
Petitioner further claims that it was denied due process since it was
never furnished a copy of the HLURB’s comment. Assuming this to be true,
petitioner had the opportunity to file a motion for reconsideration (Section 7,
Administrative Order No. 18) through which it could have refuted the comment as
well as the decision of the Office of the President but it did not do so. The
essence of due process in administrative proceedings is an opportunity to
explain one’s side or an opportunity to seek reconsideration of the action or
ruling complained of. (Arboleda vs.
National Labor Relations Commission, 303 SCRA 38 [1999].) A party cannot
feign denial of due process when he had the opportunity to present his side. (Amion vs. Chiongson, 301 SCRA 614
[1999].)
Petitioner also questions the findings of the Court of Appeals that the
property subject of the sale were not developed. This Court agrees with the
Court of Appeals that the decision of the Office of the President are supported
by substantial evidence:
x x x the HLURB found:
1. That upon a recent report submitted by their staff (attached herewith as Annex “A”) and review of the technical dockets of the entire project, the following new information were only recently brought to their attention;
a. The lots subject of this controversy are
actually not included in the approved plans and survey returns of LGV West
Ill-East IV on file with this Board, which were earlier used by our staff as
basis for the inspections and reports: rather said lots appear to be portions
of Loyola Grand Villas that have not been issued License to Sell;
b. The inspectors were apparently led into
thinking that the lots in question were part of LGV West III on the account of
the fact that the complainant’s application for Certificate of Completion, as
well as the Certification issued by Development Monitoring Office (DMO) of this
Board dated June 11, 1993, both of which form part of the references/supporting
documents incorporated/attached to the complaint filed before our Regional
Office, identified or referred to the area in controversy as “Loyola Grand
Villas West III (portion only)”, moreover, LGV West III immediately adjoins that
unlicensed portion where respondent’s lots are located;
2. That there appears to have been inadvertent misreference to the approved plans of the adjoining licensed Loyola Grand Villas West III and East in the inspection cited by the decisions of this Board.
3. That acting on the foregoing new information,
the undersigned Board Members, have caused the Regional Office to conduct a
follow up monitoring investigation of said unlicensed portion and the findings
thereon are contained in the report attached and incorporated herewith as Annex
“B.”
Substantial
evidence, which is the quantum required to establish a fact in cases before
administrative and quasi-judicial bodies, connotes merely that amount of
relevant evidence which a reasonable mind might accept to be adequate in
justifying a conclusion. (Equitable Banking Corporation vs. NLRC, 273 SCRA
352). According to the report made by the monitoring investigation committee
based on the actual records available in the HLURB (Annex “B”):
“The
following properties Blocks/Lot Nos. 7-A, 7-B, 7-E, 7-F, 7-G, 8-A, 8-B, 8-C,
8-D, 8-E, 8-F and 8-G can be located at Phase West III. Records on file show
that said Phase has not been issued a Development Permit, License to Sell nor
Certificate of Registration up to this date. The development of this Phase were
noted to be halted during the time of Inspection. Several houses were already
existing and others being built. However, land development remains to be
incomplete based on the marketing map available on file. Roadways, drainage,
sewerage, electrical facilities and waterlines, particularly the end
northeastern part of Finland and two unnamed streets perpendicular to Finland,
remain to be incomplete. Cracks already appear on roadways despite (the fact
that) few residents occupy the area. A newly installed fire-hydrant was also
noted along Hon. Benito Soliven Extension. As indicated at the said map, no
development was noted at the alleged site for the country club.”
It is
clear, therefore, that the last inspection conducted on the correct actual
locations of the subject properties show that there were indeed undeveloped
portions thereof thus justifying Sanchez’s suspension of payment of his monthly
amortization.
The filing
of the Comment amounted to an admission on the part of the HLURB that its
issuance of the assailed Resolution of February 6, 1997 was erroneous because
in resolving the issues, the Board based its resolution on the technical
records of Loyola Grand Villas East III and West IV when in fact, as asserted
in the Comment, the subject lots are not included in the approved plans and
survey returns of the LGV West Ill-East IV on file with the HLURB but rather
are included in another portion which was not fully developed and were in fact
not yet been issued a license to sell by the HLURB. Verily, the Office of the
President had sufficient basis to reverse the resolution issued by the HLURB
and reinstate the earlier decision of the Board which held that respondent
Sanchez was justified in suspending payment of his monthly amortization due to
the non-development of the properties subject of the sale x x x. (Rollo, pp. 245-247.)
Finally, petitioner contests the award of nominal damages in
respondent’s favor since, under Article 2221 of the Civil Code, “Nominal
damages are adjudicated in order that a right of the plaintiff, which has been violated or invaded by the defendant, may
be vindicated or recognized.. ..” According to petitioner, respondent was not
the plaintiff but the defendant in the proceedings before the HLURB.
Petitioner omits to state, however, that respondent in its answer (Rollo, pp. 142-148.) alleged a
counterclaim for damages against petitioner. Viewed from the perspective of the
counterclaim, respondent is the plaintiff while petitioner is the defendant. As
petitioner, by its failure to fully develop the property pursuant to its
obligation, violated respondent’s rights under said contracts, respondent is
entitled to nominal damages, with no need of proof of pecuniary loss. (Article
2216, Civil Code.) While respondent did not explicitly pray for an award of
nominal damages in its counterclaim, he did pray for “such other reliefs as may
be deemed just and equitable under the premises.”
IN VIEW OF THE FOREGOING, the
Court Resolved to DENY the petition.
Very truly
yours,
(Sgd.)
VIRGINIA ANCHETA-SORIANO
Clerk of
Court